Logistics platform for prompt delivery for LMC Group

Case study

With the conception and realization of the new distribution center of the French LMC Group, Körber has created one of the most modern logistics centers in France.

Share

LMC Group logo

Results

4‑aisle automated high‑bay warehouse with 6,000 pallet positions

The new distribution centre includes a four‑aisle high‑bay warehouse offering 6,000 pallet storage locations in a compact, silo‑style rack system.

Up to 192 pallet moves per hour

Four stacker cranes with double‑cycle capability deliver a throughput of 192 storage and retrieval movements per hour, ensuring fast material flow. 

~1,000 orders/day with rapid delivery

About 1,000 customer orders per day are processed through integrated IT and automation, enabling delivery of orders placed before noon within 24–48 hours.

Unlock the full case study